OWNER: OTIC & Cuyahoga County Department of Public Works

PROJECT COST/VALUE: $13.07M

QCS FEE:  $658,967

ROLE: Subconsultant/Construction Management and Inspection

PROJECT DURATION: 2 years

QCS STAFF & SERVICES PERFORMED:          

  • Zak Klepek (Resident Engineer)
  • Zack Schlessman (Project Inspector/Structures Inspector)
  • Steve Mileski (Project Inspector)
  • Jeff Zaucha (Project Inspector)
  • Johnny Webb (Coatings Inspector)

SERVICES PERFORMED:

  • Resident Engineer: Managed project from start to finish
  • Project Inspection for the following: new sanitary and storm sewers; new concrete pavement; new curbs; new castings; new sidewalks; new commercial/residential drive aprons; multiple MOT phases; new traffic and pedestrian signals at Schady Road and Bagley Road intersections with Stearns Road; new guardrail; new mailboxes
  • Structures Inspection for the following: replacement of three bridge decks including bearings, parapet walls,  approach slabs and anti-vandal fencing
  • Coatings Inspection: performed inspection for coating of new bearings and beam ends on all three bridges

PROJECT DESCRIPTION: QCS provided construction management and inspection for this two-year project which included the removal and replacement of three bridge decks (Stearns Road and Race Road Bridges over the Ohio Turnpike and an Ohio Turnpike Ramp over State Route 57) and the reconstruction of Stearns Road between Bagley Road and Schady Road. In addition to the bridge decks, the approach slabs and parapet walls for all three bridges were removed and replaced. Stearns Road also had a brand new sanitary mainline installed between the Stearns Road bridge over the Ohio Turnpike and Schady Road, including sanitary laterals. Along with the sanitary sewer, a new storm sewer system was installed along Stearns Road. Lastly, the existing Stearns Road pavement was replaced with new full-depth concrete pavement that included a widened driving area and dedicated turn lanes at both the Stearns/Schady and Bagley/Stearns intersections. New signals were installed at the two intersections to accommodate these additional lanes. In addition, new curbs, sidewalks and business/resident drive aprons were installed along Stearns Road between Schady Road and Bagley Road.