Project Description
Hands Free Mooring Slots Installation – Snell Lock – Saint Lawrence Seaway Development Corporation – USDOT
Scope: The installation of three sets of 75 LF vertical rails in the North Wall Monolith of Snell Lock – Massena, NY
Project value: $6.9 million
Project duration per phase:
Phase I: November 2017 – March 2018
- The installation and testing of 18 x 55 lf long post tensioned rock anchors
- Demolition: 1,150 CY of concrete demolished using heavy duty grinders mounted on excavators operating from barges in the lock; demolition limits survey and corrections.
- Concrete base and temporary concrete bulk heads pour
Phase II: January 2019 – March 2019
- Temporary concrete bulk heads demolition
- Dowel and anchor rods installation and testing in the vertical walls
- Rails installation, alignment and survey
- Pouring structural concrete: reinforcing bars installation, forming and concrete pouring in 3 lifts per slot, approximately 780 CY of concrete poured in total.
- Electrical conduits and bubbler pipe system installation
- Work on top of the deck: concrete pedestals (plinths) pouring, anchor bolts installation and testing
Project special conditions:
- Work in the lock which is mandatory during the navigation off-season
- Rail alignment within +/- 2 mm tolerance in all planes
- Concrete pouring in heated enclosures due to extreme winter weather conditions
QCS performed the Third Party Inspection for this project with three inspectors covering the General Contractor’s schedule of 7 days per week working 12 hour shifts (day and night). Our General Construction Inspection duties included the following:
- Post Tensioned rock anchors installation and testing inspection
- Demolition limits assessment
- Dowel and anchor rods installation and testing inspection
- Rail alignment assessment during the alignment procedure and following survey
- Reinforcing bars installation inspection
- Concrete testing (all delivered concrete was tested on site) and concrete placement Inspection
- Checking critical dimensions of slot geometry (during forming and corner protection plate positioning)
- Conduits and bubbler pipe system installation inspection
- Painted steel touch up operation inspection.