Project Description
OWNER: Lorain County Sanitary Engineer
PROJECT COST/VALUE: $1.87M
QCS FEE: $100,000
ROLE: Subconsultant/Construction Administration and Construction Inspection
ESTIMATED PROJECT DURATION: 4 months
QCS STAFF & SERVICES PERFORMED:
- Matt Pawlak (Project Manager)
- Scott Slack (Assistant Project Manager)
- Keith Jones (Construction Inspector)
SERVICES PERFORMED:
- Construction Inspection during installation of the Boone Road Phase 3 Sanitary Sewer
SCOPE: QCS will be responsible for all construction administration and inspection associated with the project including the following:
- Production of daily inspection reports
- Monitoring and reviewing employee prevailing wages
- Review and recommend change orders
- Prepare monthly contractor invoices
- Monitor air and mandrel testing
- Review and approve material and shop drawings
PROJECT DESCRIPTION: QCS will be providing Construction Administration and Construction Inspection for this project. The project was awarded to Fechko Excavating and includes the installation of 3276 linear feet of 21 and 24 inch diameter sanitary sewer running southerly from the intersection of Boone Road and State Route 82 and will service the new Del Webb development. Manholes, sanitary laterals and pavement repairs are included with this project.